For Site Owners and Developers
Turn a grid allocation
into powered land.
Buyers pay for energized land. Bridge power makes a site energized before the grid does.
- AllocationBatch Zero capacity allocated
April 9 – June 8, 2027
- BridgeNeoCore power on site
Weeks from notice to proceed; permanent gas generation in ~9–12 months
- GridTransmission capacity delivered
2028–2032; loads not served in the window roll to 2033
Batch Zero dates per ERCOT PGRR145 / NPRR1325 and PUCT Docket 58481.
What we bring to a Batch Zero site
- Bridge generation in 10–30 MW blocks, modular and redeployable as permanent capacity comes online
- Bolt-on behind-the-meter capacity to expand beyond the grid allocation
- Fuel path by geography: CNG within ~200 miles of our Permian compression; diesel bridge beyond
- Emissions and air-permit pathway, including sites in non-attainment zones
- A three-to-five-year primary bridge with a ten-year backup tail; the plant stays as backup when the grid arrives
- One counterparty for fuel, generation and operations, structured to transfer to a successor owner
The window
Power is allocated in spring 2027. A site with committed bridge power in hand sells as powered land; a site without one waits for the grid.
Is your site a fit?
- Distance to our gas supply
- Pipeline adjacency
- Acreage and target load
- Allocation year sought
Grid + BTM
More megawatts sooner, and a stronger exit.
Behind-the-meter capacity on top of your grid allocation, from the team behind our 200+ MW hyperscaler bridge program.
| Dimension | Starter · 25–75 MW | Mid-scale · 100–200 MW | Large campus · 300 MW+ |
|---|---|---|---|
| What we deploy | Portable diesel gensets for first power; gas recips for the permanent block | 3–15 MW gas modules stacked into power islands, with BESS for firm uptime | Aero and industrial gas turbines plus recips in power islands, with BESS |
| Fuel path | Diesel bridge, CNG virtual pipeline | CNG until the lateral is in service; pipeline gas after | Pipeline gas on firm transport; CNG as backup |
| Permitting path | Portable-unit route for bridge power | Air permit, ~6-month minimum | Air permit and emissions plan, including non-attainment zones |
| Bridge power | ≤120 days, where required | ≤120 days, where required | ≤120 days for an initial block, where required |
| Permanent power | First block in ~9–12 months | First block in ~9–12 months | First block in ~9–12 months, then phased blocks |
Let’s energize your site.
Share your load, location, required date and availability target. An indicative plan follows within one week of our technical exchange.